Case study

Finding better schedules for complex projects

Scheduling hundreds of interdependent activities under limited resources creates an enormous number of possible plans. A small improvement in the sequence of work can shorten the overall completion time, but finding that improvement may require sophisticated search across tightly constrained alternatives.

4colors developed scheduling algorithms that produced new best-known results on long-established resource-constrained project-scheduling benchmarks, including instances where the resulting schedule matched a published mathematical lower bound.

Organization
4colors
Type
Benchmark
Focus
Resource-constrained project scheduling

The challenge

Project scheduling involves deciding when activities should start and how limited resources should be allocated.

Some tasks must finish before others can begin. Several activities may need the same equipment or people, and changing one start time can affect the entire schedule.

The RG300 benchmark contains problems with 300 activities and defined resource constraints. Researchers have used these instances for years to compare optimization algorithms.

Our approach

4colors developed and refined optimization algorithms to search for improved schedules across the benchmark.

The work combined mathematical modeling with computational search, evaluating candidate schedules against the same precedence and resource constraints used in the published problems.

The algorithms explored combinations that earlier methods had not improved upon.

The work

The algorithms were tested on the RG300 benchmark family, where projects contain 300 activities subject to precedence and shared-resource constraints. Comparing schedules against established best-known results and published lower bounds provides a reproducible measure of progress.

The outcome

The algorithms produced 119 new best-known RG300 schedules in 2026, including 49 first reported improvements to results dating back to 2007. For the instance RG300_70, the completion time improved from 634 to 630 benchmark units, matching its published lower bound. Across the reported results, 11 instances matched published lower bounds. The comparison uses published records as of October 29, 2026.

Commercial relevance

A benchmark record is meaningful because the problem definition and comparison are fixed. Each RG300 instance has precedence and resource constraints, and a shorter feasible schedule is a measurable improvement. Matching a mathematical lower bound is stronger still: it establishes that no better completion time is possible under the benchmark's assumptions.

These results reflect the core commercial strength of the 4colors Optimizer: tailored algorithms that search difficult scheduling spaces efficiently and continue improving solution quality. They provide independently checkable evidence of progress in the computational methods used for real scheduling problems.

The same mathematical difficulties appear in manufacturing, engineering, construction and other operations involving interdependent tasks and limited resources.

Better algorithms can uncover schedules that were previously out of reach, giving planners more effective options without changing the resources available.

Working on a similar problem? Discuss your challenge